Princeton Infrastructure Project – Final Stage Update

Back to Search

The Township of Blandford-Blenheim is pleased to share an update on the Princeton capital project, now entering its final stage of construction.

Current Work

  • Curb installation has begun, and crews are rebuilding the road base throughout the village.

  • The final phase of underground storm sewer work at the south end of Princeton is scheduled for completion within the next two weeks.

Next Steps (4–6 Weeks)

  • Installation of all curbs

  • Completion of roadwork and paving of asphalt on roads and driveways

  • Application of topsoil and sod to restore landscaped areas

To help reduce dust during construction, a dust suppressant will be applied on Friday, September 19, 2025.

Thank You

We extend our sincere thanks to Princeton residents and businesses for their patience and cooperation throughout this three-year project. Your support has been vital as we invest in long-term infrastructure improvements for the community. The finish line is in sight, and we look forward to unveiling a refreshed and revitalized Princeton.